Wind Farm Zeewolde

We proudly present our successful contribution to the Zeewolde Wind Farm. Windpark Zeewolde B.V. is owned by a unique collaboration of more than 200 farmers, residents and entrepreneurs from the outskirts of Zeewolde. With 83 wind turbines and a total capacity of 322 MW, this is the largest onshore wind farm in the Netherlands.

The 200 scattered older windmills made way for 83 larger, more modern turbines. Together, these generate more than twice as much energy as the old mills. The Zeewolde Wind Farm thus provides green energy for approximately 300,000 households.

Our role included close coordination with various parties involved, including contractors, electrical engineers, mechanical engineers, customers and turbine suppliers. Through our efficient execution and quality assurance, we have not only met deadlines, but also ensured optimal performance and sustainable success.

The project was realized in the outskirts of the municipality of Zeewolde, north of the A6 and west of the A27. The construction of the wind farm started in 2021 and completed in 2022. The park is expected to be operational for 25 years.

Want to see our project live? Yes, you can do that via: https://youtu.be/HO90Fi6ZXR8

Type

Designs and calculations

Opdrachtgever

Omgeving

Zeewolde

Tijdsduur

2019 - 2022

Rol VORM4

Architect

Ontwikkelaar

Installatieadviseur

Aannemer

Projectmanagement

Bouwmanagement

Bouwfysica

Installatietechnisch adviseur

1.384.736
tons of emission savings
300,000
residents on green electricity
445
tons of mill weight analyzed
Uitdaging

Realizing a large-scale wind farm without delays

Zeewolde Wind Farm had an ambitious goal: to triple the energy yield by replacing 220 obsolete windmills with 83 advanced ones.

This had to be done within a tight schedule and without sacrificing quality and safety. But complex challenges quickly arose:

  • Engineering bottlenecks: The original design had to be tested and aligned with the implementation specifications.
  • A crucial change of turbine supplier: Halfway through the project, we had to switch from Enercon to Vestas, with major consequences for engineering and planning.
  • Tight deadlines and high expectations: Implementation planning should not be compromised at any time.
Oplossing

Make various calculations and simulations to recommend the right foundation

Ultimately, it took 68 kilometers of piles, 4,100 tons of reinforcing steel, 42,000 tons of concrete to provide the windmills with the right foundation. Our expertise ensured that each windmill was installed down to the millimetre. Years later, they are still exactly where they were placed - a tangible proof of our expertise and dedication.

Laten we slim & samen ontwikkelen

Klaar om bewust voor innovatie, efficiëntie en duurzaamheid te kiezen? Heb je ideeën die staan te trappelen om werkelijkheid te worden? Stuur ons een bericht!

No items found.
Bouwen zonder verrassingen

Andere projecten

Ready to give your project a boost? Do you have ideas that are eager to become a reality? Send us a message! We're here to listen, brainstorm and create something great together